Project milestones

2016  
15th April 2016

The Ministry of Environment of the Slovak Republic has issued the Final Statement for Jadrová energetická spoločnosť Slovenska, a. s. (JESS) for the project of the New Nuclear Power Plant (NNPP) in Jaslovské Bohunice site in which it has recommended implementation of the proposed activity in terms of its environmental impact.

2015  
21st December 2015 Extraordinary General Assembly of the company JESS approved the merger of the subsidiary JESS Invest with the company JESS, while company JESS remained the successor company.
3rd – 4th December 2015 In Ukraine, in the city of Kiev, there was a cross-border public hearing and expert consultations held.

25th – 26th November 2015

In Germany, in the city of Munich, there was a cross-border public hearing and expert consultations held.

18th – 19th November 2015

In Austria, in the city of Vienna, there was a cross-border public hearing and expert consultations held.
27th October 2015

In Hungary, in the city of Győr, there was a cross-border public hearing and expert consultations held.

23th September 2015 Following the publication of the Report the joint public hearing on the proposed activity has been hold on the level of concerned communities at the community centre in Veľké Kostoľany.
2nd September 2015 The Ministry of Environment of the Slovak Republic has issued The Environmental Impact Assessment Report of the Proposed Activity determined in accordance with the Act No. 24/2006 Coll. on environmental impact assessment.
2014  
30th September 2014 The Ministry of Economy of the Slovak Republic issued the Certificate for the Construction of an Energy Facility entitled "New Jaslovské Bohunice Nuclear Source with the Capacity of Up to 1,200 MWe."
30th July 2014 Jadrová energetická spoločnosť asked the Ministry of Economy of the Slovak Republic to issue the Certificate for the Construction of an Energy Facility.
26th May 2014 The Ministry of Environment of the SR has issued The Scope of the Proposed Activity Assessment determined in accordance with section 30 of the Act No. 24/2006 Coll. on environmental impact assessment.
19th March 2014 Member of the Board of Directors, Ing. Tomáš Vavruška presented the topic of the current steps and the challenges that await the NNPP project in the near future at the meeting of the ATM Council – Association of Towns and Municipalities of the Jaslovské Bohunice nuclear power plant region, held in Piešťany.
11th March 2014 At the meeting of The Bohunice Citizen Information Commission (CIC) in Veľké Kostoľany, Chief Executive Officer Ing. Štefan Šabík informed about the progress of the NNPP project to the next stage within the EIA process, which was the submission of Preliminary Study for the Proposed Activity to the Ministry of Environment of the SLovak Republic.
05th March 2014 The Preliminary Study for the Proposed Activity was transmitted to the Ministry of Environment of the Slovak Republic.
2013  
26th Sptember 2013 At the tenth International SES (Secure Energy Supply) Conference, designated for experts from the nuclear and energy industries, the CEO spoke about the initiation of the NNPP project’s environmental impact assessment process.
Sptember 2013 The most important project milestone in 2013 was the launching of the environmental impact assessment process (EIA), the invitation to a tender for an EIA elaborator completed, and a contract with AMEC signed.
The initial work related to the assessment process began that month, and it should reach completion by mid-2016.
24th April 2013 At the 2013 ENK O conference, held in Bratislava, the CEO presented “A New Nuclear Power Plant – the Conclusions of the Feasibility Study and Further Project Procedure.”
15th January  2013 JESS, in the presence of other interested parties (JAVY S, ČEZ, and ČEZ Bohunice) signed a memorandum of cooperation with Rosatom, allowing a third party to obtain information about the status of the new  nuclear power plant project.
2012  
28th November 2012 At the “Current Projects at the Jaslovské Bohunice Nuclear Energy Site” workshop held in Veľké Kostoľany, the general director of JESS presented current activities and the outlook for a new nuclear plant to be developed. The seminar was organised by OIK Bohunice in cooperation with the Jaslovské Bohunice Regional Association of Municipalities.
28th Sptember 2012 At a meeting of OIK Bohunice in Veľké Kostoľany, the general director briefed members about the main conclusions and recommendations produced from the Project NNPP Feasibility Study.
27th Sptember 2012 At the Secure Energy Supply (SES) international conference, JESS's general director spoke about the main conclusions drawn from the Feasibility Study and reported on the state of preparations for constructing a New Nuclear Power Plant in Slovakia.
26th July 2012 Feasibility Study prepared to judge key aspects of Project NNPP, forming a critical base for further consideration of the project.
2011  
24th November 2011 Signing the Contract for Work for the elaboration of the Feasibility Study and related studies for the Project of the New NPP in Jaslovské Bohunice site.
September 2011 Delivery of bids for the tender to select the Contractor of the Feasibility Study.Selection of the Feasibility Study Contractor was closed.
July 2011 Tender documentation for the preparation of the Feasibility Study were sent to ten selected applicants.Conclusion of the Contract for Work to execute the Seismicity and Geological Relation Assessment Study for the project of the New NPP in Jaslovské Bohunice site.
May 2011 The final evaluation of information packages sent from six contractors of the New NPP, based on the Request for Information document, which form one of the basic data for preparation of the Feasibility Study.
April 2011 The model for concluding an agreement and preparation of the Feasibility study was approved.
2010  
November/December 2010 We received the information packages from all invited potential supplier of New NPP as a basis for preparation of the Feasibility Study.
10th August 2010 Company’s management made a decision to prepare a part of the feasibility study by own staff - by means of reviewing and using own and public accessible information sources and information from information packages of the contractors.  
August 2010 All potential contractors of the main contract were addressed to which at the same time a document of questions to their project was sent.   The information from the contractors is necessary to prepare a Feasibility Study and Environmental Impact Assessment process.  
May/June 2010 Meetings with and visits of possible main contractors to Jaslovské Bohunice site.
2009  
31st December 2009 Jadrová energetická spoločnosť Slovenska, a. s., was incorporated into the Commercial Registry of the Slovak Republic.
9th December 2009 Decree of Government of the Slovak Republic No 893/2009
The government of the Slovak Republic approved the foundation of power company Jadrová energetická spoločnosť Slovenska, a. s., Jadrová energetická spoločnosť Slovenska, a. s. will be responsible for preparation, construction and operation of a new nuclear power plant in Jaslovské Bohunice.
4th November 2009 The European Commission approved the proposed establishment of a joint venture between Jadrová energetická spoločnosť Slovenska, a. s., shareholders of which are ČEZ Bohunice a. s. and Jadrová a vyraďovacia spoločnosť, a. s.
29th May 2009 On occasion of 4th Session of European Nuclear Forum in Prague, representatives of power companies JAVYS and ČEZ signed a Shareholding Contract which enables them to establish the joint venture for construction of new nuclear power plant in Jaslovské Bohunice in Slovakia.
27th May 2009 Decree of Government of the Slovak Republic No 408/2009
Proposal of procedure for foundation of a joint venture between JAVYS, a. s., and ČEZ, a. s.
2008  
17th December 2008 Decree of Government of the Slovak Republic No 948/2008 A new nuclear power plant in Jaslovské Bohunice site.
7th May 2008  Decree of Government of the Slovak Republic No 275/2008 The proposal of possibilities for assuring the construction of new nuclear power plant in Jaslovské Bohunice site.
 

 

In Ukraine, in the city of Kiev, there was a cross-border public hearing and expert consultations held.